HV Substation Testing & Commissioning: Complete Checklist

Writer: VSS Power
VSS Power
15 minutes ago
6 min read

HV substation testing and commissioning checklist

In July 2018, an oil sample from a transformer bushing at the North Hyde 275 kV substation showed increased moisture. No appropriate actions were taken due to its severity [1]. On 20 March 2025, the transformer was impacted by fire, almost certainly after some moisture had seeped into the bushing. Heathrow Airport was closed for most of the next day [1]. 


That was an in-service failure, not a commissioning one. But it shows why HV substation testing & commissioning matters: test data only protects an asset if someone acts on it. 

This guide covers: 

  • What to test, and in what order 

  • What the data says about risk 

  • A worked cable-test calculation 

  • Practical steps for UK, European, Middle East and Indian projects 


Why is substation commissioning under pressure now? 


Short answer: a very large pipeline of projects is heading for energisation. 

  • GB's old connection queue grew to over 700GW, some four times the requirement for 2030 [2]. 

  • The reformed pipeline holds 283 GW of generation and storage, plus 99 GW of transmission demand [2]. 

  • Interpretation: every energisation window matters more, and test teams and equipment become scarce. 

GB connections pipeline after Connections Reform

Reliability data shows why early testing pays: 

  • CIGRE have recorded 1,204 major transformer failures (100kv and above) over 425,000 transformer years. That's approximately 0.28% per year [4]. 

  • CIGRE's 2004–2007 SF6 breaker survey logged 840 major and 6,655 minor failures in 281,090 breaker-years [5]. Minor failures outnumbered major ones by 8 to 1. 

  • Interpretation: major failures are rare. Small defects are common, and substation commissioning is the cheapest point to find them. 

What does a complete HV substation testing and commissioning checklist include? 


Short answer: a complete HV substation testing and commissioning checklist proves, in order, that the site is built as designed, safe to energise and compliant with the network operator. 


Electrical asset failures


Step-by-step HV substation commissioning procedure 


  1. Documents and civil checks. Review as-built drawings, test plans and punch lists. Check civil and structural design items: foundations, oil bunds, cable trenches and fire barriers. 

  2. Earthing. Test continuity and resistance, then verify step and touch voltages. In GB, ENA TS 41-24 and BS EN 50522 are the usual references. 

  3. Power transformer testing. Turns ratio, winding resistance, insulation resistance, power factor and capacitance (including bushings), frequency response, oil moisture and dissolved gases. IEEE C57.152-2025 is the current field-testing guide [8]. 

  4. Circuit breaker testing. Contact timing, contact resistance, insulation resistance, SF6 density, and trip and close coil checks, per manufacturer instructions. 

  5. Instrument transformers. Ratio, polarity and burden. 

  6. HV cables. Voltage testing means a DC sheath test and an AC withstand test on the main insulation, plus partial discharge (PD) measurement [6]. 

  7. Secondary systems. Protection injection, trip chains, interlocks, SCADA point-to-point and auxiliary supplies. 

  8. Energisation. Staged energisation, then on-load checks. 

  9. Network compliance. In GB, for generation connections: EON for first energisation, ION for first export, FON once all issues close [7]. 

How much power does a cable withstand test need? 


Short answer: about 4 MVA for 5 km of 132 kV cable. Size the high-voltage cable tester before booking the outage. 

 

  • Test voltage: 1.7 U₀ for 60 minutes at 132 kV, typical for this class [6]. 

  • U₀ = 132kv/ √3 = 76.2kv. Test voltage = 1.7 x 76.2 = 129.6kv. 

  • Capacitance (assumed): 0.15 µF/km x 5 km = 0.75 µF. Use the value you measure on site. 

  • Charging current: I = 2πfCV = 2π × 50 × 0.75 × 10⁻⁶ × 129.6 × 10³ ≈ 30.5 A. 

  • Reactive power: Q = V × I ≈ 3.96 MVA. 

What it means: 

  • A resonant set rated 260kV and 83A (as used in one lab's cable testing [6]) will cover 129.6 kV and 30.5 A. Check the rating at your test frequency. 

  • Current scales with length. At 10 km, expect about 61 A at the same voltage. 

  • Higher voltages require more kit. INMR notes that tests above 260kV will require at least two resonant units or an additional insulated reactor, and long circuits may well require units in parallel for power [6]. 

  • Check the system quality factor too. INMR notes that values under 100 can indicate corona or poor earthing [6]. 

Why it matters (one laboratory, mostly Spanish projects, so indicative only [6]): 

  • 800 plus circuits tested, from 36/66 kV up to 220/400 kV. 

  • 4.5% failed at least one commissioning test. 

  • Main insulation failures: 3.1% (approx. half breakdown, half early PD). 

Share of HV cable circuits failing site commissioning tests

Benchmark 

Population 

Result 

Source 

Transformers ≥100 kV, major failures 

425,000+ transformer-years 

1,204 failures, about 0.28% a year 

CIGRE TB 939 [4] 

SF6 breakers ≥60 kV, major failures 

281,090 breaker-years 

840 failures, about 0.30 per 100 breaker-years 

CIGRE TB 510 [5] 

HV cable circuits at commissioning 

800+ circuits 

4.5% failed a test 

INMR/Tecnalia [6] 

Definitions and populations differ, so do not compare rows directly. Rates are the author's calculations. 


What should engineers do differently? 


  • Confirm test plans and acceptance criteria with the manufacturer and operator prior to the site work. 

  • Obtain your HV testing equipment early: resonant sets, PD detectors, calibration certificates. 

  • Remove or isolate the voltage transformers at the GIS before cable AC tests. INMR have warned of high-frequency transient damage [6]. 

  • Close or formally accept every punch list item prior to energisation. 

  • Record every factory and site reading as a baseline. On-site tan delta is essentially just a reference point for future trends [6]. 

  • Name an owner and a deadline for every out-of-range result. That is the North Hyde lesson [1]. 

  • Start GB compliance early. NESO's first compliance panel meets 18 to 12 months before energisation or export [7]. 

  • Apply the same discipline to power plant testing and commissioning for solar, wind and BESS connections. 

  • Confirm regional rules. EON, ION, and FON are GB processes. European, Middle Eastern and Indian projects follow their own utility or grid-code specifications. 

  • Never shorten safety steps to save outage time. Electrical and Power Engineering teams should follow site safety rules and the project specification. 

What comes next? 


  • IEEE C57.152 has been revised. The 2025 edition was published in June 2026 [8]. 

  • CIGRE says solar and wind-farm transformers lack enough service-years for firm statistics [4]. Interpretation: commissioning baselines are the best evidence available. 

  • GB Phase 1 projects are targeted at 2030 and Phase 2 at 2035 [3]. Demand for test capacity will continue. 

Substation and grid compliance process

Conclusion 


The data points one way. Major failures are very rare, small defects are the norm and they're relatively cheap to find during commissioning. The calculation is that test power has to be planned right at the outset and North Hyde shows that the results have to be acted upon. 

If you need substation testing and commissioning services in the UK, VSS Power can discuss your project scope. 


Key Takeaways 


  1. Act on test data. A bushing moisture reading in July 2018 preceded the 20 March 2025 North Hyde fire [1]. 

  2. Major failures are rare. CIGRE data gives about 0.28% a year for transformers of 100 kV and above (1,204 failures in 425,000+ transformer-years) [4]. 

  3. Small defects are common. SF6 breakers logged 6,655 minor failures against 840 major failures in 281,090 breaker-years [5]. 

  4. Site workmanship is important. 4.5% of the 800 plus HV cable circuits in one laboratory's data failed at least one commissioning test. [6] 

  5. Plan your test power early. 5 km of 132kV cable will require around 30.5A and 3.96MVA at 1.7U₀ (just an illustrative calculation). 


FAQs 


What is HV substation testing and commissioning?  

It is the staged process of proving that a high-voltage substation is built as designed and safe to energise. It covers earthing, primary plant, cables, protection and control tests, followed by staged energisation, network compliance and handover to the operator. 


What tests are done on a power transformer before energisation?  

Typical site tests include turns ratio, winding resistance, insulation resistance, power factor and capacitance (including bushings), frequency response and oil analysis. IEEE C57.152-2025 gives diagnostic field-testing guidance, and the manufacturer's acceptance criteria may take precedence over it [8]. 


How is a high voltage cable tested after installation?  

IEC 60840 and IEC 62067 cover voltage withstand tests on the main insulation and sheath. In practice, this means a DC sheath test, an AC withstand test, usually for 60 minutes, and partial discharge measurement, which is recommended particularly at transmission voltages [6]. 


What are EON, ION and FON in Great Britain?  

EON is the notification needed for first energisation of a new connection. ION is needed for first export to the transmission system by a new generator. FON is issued once all issues identified in the ION are resolved. They are GB Grid Code processes [7]. 


Why do HV cable circuits fail commissioning tests?  

In one laboratory's results from 800+ circuits, 4.5% failed at least one test. Joints were usually the weakest component where sheath problems occurred, with partial discharge linked to improper assembly, most often at 66 kV. Accessory workmanship is therefore a key focus [6]. 


References
  1. National Energy System Operator (NESO), “Final report from the review into the North Hyde Substation outage”, 2025.

    https://www.neso.energy/news/final-report-review-north-hyde-substation-outage

  2. NESO, “Unveiling the new project pipeline to deliver Clean Power by 2030”, 8 December 2025. https://www.neso.energy/news/unveiling-new-project-pipeline-deliver-clean-power-2030

  3. PV Tech, “UK’s grid reform separates viable projects from zombies” (reporting NESO results), 2025. https://www.pv-tech.org/uks-grid-reform-separates-viable-projects-from-zombies/

  4. CIGRE WG A2.62, Technical Brochure 939, “Analysis of AC transformer reliability”, 2024.

    https://www.e-cigre.org/publications/detail/939-analysis-of-ac-transformer-reliability.html

  5. CIGRE WG A3.06, Technical Brochure 510, “Final Report of the 2004–2007 International Enquiry on Reliability of High Voltage Equipment, Part 2: SF6 Circuit Breakers”, 2012.

    https://e-cigre.org/publication/510-final-report-of-the-2004---2007-international-enquiry-on-reliability-of-high-voltage-equipment---part-2-sf6-circuit-breakers

  6. INMR (Tecnalia Electrical Laboratories), “Commissioning Testing HV Power Cables”, republished 2026. https://www.inmr.com/commissioning-testing-hv-power-cables/

  7. NESO, “Compliance Process”, accessed 23 November 2026.

    https://www.neso.energy/industry-information/connections/compliance-process

  8. IEEE SA, “IEEE C57.152-2025, Guide for Diagnostic Field Testing of Liquid-Filled Power Transformers, Regulators, and Reactors”, published 2 June 2026.

    https://standards.ieee.org/ieee/C57.152/7662